Site Designs Presented January 9, 2008

Site Scheme One

Site Scheme One

Strengths

Worship space is primary focus of site entry

Court opens to view

Opportunity to share facilities with school

School has direct access to playing fields

Clear drop-off and pick-up routes

Easy pedestrian circulation between buildings

Weaknesses

Worship space close to future arterial road

View is over parking lot

Parking configuration creates multiple entry points to worship space

Requires 13th to be extended to Linden Avenue

Site Scheme Two

Site Scheme Two

Strengths

Buildings located away from future arterial road

Worship space has east-west orientation

Works well with slope of site

School has direct access to playing fields

Good distribution of parking/day chapel parking

Easy pedestrian circulation between buildings

Weaknesses

Drop-off/pick-up sequence

Fire fighting access on north side

Southwest corner of site undeveloped

Entry road does not support future development to the north

Opportunity to share facilities with school

Views to the north from all buildings

South facing court

Site Scheme Three

Site Scheme Three

Strengths

Worship located away from future arterial road

Worship space is primary focus of site entry

Works well with slope of site

School has direct access to playing fields

Good distribution of parking/day chapel parking

Weaknesses

Drop-off/pick-up sequence

Fire fighting access on north side

Southwest corner of site undeveloped

Opportunity for school/church shared uses limited

School drop-off/pick-up

Pedestrian connection to the north

South facing court

Site Scheme Four

Site Scheme Four

Strengths

Court opens to view

Entry road supports development to the north

School has direct access to playing fields

Clear drop-off and pick-up routes

Weaknesses

Worship space close to future arterial road

Parking is remotely concentrated

Opportunity for school/church shared uses limited

Requires 13th to be extended to Linden Avenue

 

Site Design January 10, 2008

Site Scheme Five

The design team took comments from the Wednesday evening parish meeting and incorporated them into a revised master plan that was acknowledged by the building committee as combining the best features of the other plans presented.

     

Site Scheme Five

Strengths

*Main entry is at worships side of the site

*Strong visual connection between school and worship

*Potential future access of of Bryden Ave.

*Relationship to natural area/ravine

*Two story school reduces footprint

*Play areas are sheltered/accessible

*Courts face to the south

*Pedestrian paths are separated

*Drop-offs work well

*Dual entries

*Availability of utilities

*Preservation of a large part of the site for future revenue generation development

*Multiple buildings support/facilitate phasing (building in stages)

*Multiple building reduce scale

Weaknesses

*Soccer fields require grading

*Access from 13th Street enters into parking lot

*Pedestrian path crossed by service access